INTRODUCTION
Alatas UK was requested to attend an offshore platform to prepare the crane for welding repairs at the apex and to carry out the replacement of the apex sheaves and pin.
BACKGROUND
The crane had recently undergone an overhaul; however, several tasks remained outstanding. These included the replacement of the apex sheaves and pin, as well as welding repairs due to corrosion at the apex. Since the welding could not be performed with the ropes and sheaves in place, their removal created an ideal opportunity for Alatas technicians to complete the outstanding mechanical work.
ALATAS’ SOLUTION
The first step involved removing the boom ropes. Due to limited deck space, only one spooler could be used. This spooler was positioned behind the crane prior to the start of the job.
Following pre-work checks, the right-hand boom rope was removed, replaced with a softline, and secured to a strong point, allowing the rope to be coiled on deck in a figure-eight configuration. The same method was applied to the left-hand rope, though this rope was fully spooled onto the drum.
With the ropes removed and a softline holding the reeving pattern in place, scaffolding was erected at the apex. Using a lift plan developed specifically for this scope, the technicians removed the old sheaves and pins. Once removed, the area was made safe and handed over for welding repairs.
After welding was completed, new sheaves and pins were installed, again in accordance with the job-specific lift plan. The ropes were then reinstalled.
Final commissioning involved load testing using a client-supplied water bag and calibrated load cell. All equipment was inspected and certified prior to the test, which was carried out in accordance with Alatas’ Load Test Guidance.
JOB SCOPE
- Conduct Pre-Work Checks
- Remove Right-Hand Boom Rope and Replace with Softline
- Coil Rope in Figure-Eight on Deck
- Remove Left-Hand Boom Rope and Replace with Softline
- Remove Old Sheaves and Pin
- Hand Over Worksite for Welding Repairs
- Install New Sheaves and Pin (per Lift Plan)
- Reinstall Boom Ropes
- Load Test and Commission Crane