Overview
Alatas Poland replaced the hoisting gearbox and hydraulic motor on a 36-tonne TTS deck crane while the vessel remained at anchorage, returning the crane to full operational duty without requiring deviation to a shipyard. The project included the removal of a seized hoisting gearbox, installation of a replacement gearbox and hydraulic motor, and successful completion of dynamic and static proofload testing.
Background
The No. 3 deck crane on a geared bulk carrier had developed a defective hoisting gearbox that could no longer be relied upon for cargo operations. Replacing a hoisting gearbox is normally performed during dry dock; however, this project was completed while the vessel remained at anchorage.
The gearbox had seized into the crane side plate, and a standard mechanical press was insufficient to release it. Completing the repair in the field required careful rigging, custom tooling, and close coordination with the ship’s officers and crew.
Alatas’ Solution
An Alatas Poland service engineer attended the vessel and worked closely with the ship’s officers and crew to complete the gearbox replacement safely at anchorage.
Access to the hoisting system was achieved by removing the slip ring, hoisting limit-switch box, hydraulic motor, and protective gratings. When the mechanical press could not release the seized gearbox, the team employed a hydraulic press and jack before fabricating custom expanders on site to free the drum-and-gearbox assembly from the crane side plate.
The existing gearbox was separated from the drum, contact surfaces were cleaned and inspected, and a new hoisting gearbox and hydraulic motor were installed. Gearbox bolts were torqued to 1,220 Nm using a calibrated torque wrench with Loctite 270, gearbox oil was replenished, and the slip ring and limit switch were reinstated. The hoisting wire was fully re-tensioned on the drum before the crane completed a dynamic load test at the nominal 36-tonne SWL and a static proof load test at 41 tonnes (SWL + 5 tonnes).
Job Scope
- Attend the vessel at anchorage and conduct toolbox talks and risk assessments with the ship’s command.
- Remove the slip ring, hoisting limit-switch box, hydraulic motor, and protective gratings.
- Slacken and secure the hoisting wire using the emergency brake-release system.
- Free the seized gearbox using a hydraulic press, hydraulic jack, and purpose-fabricated expanders.
- Extract the hoisting drum and separate the existing gearbox.
- Clean and inspect gearbox contact surfaces.
- Install the new hoisting gearbox.
- Torque gearbox bolts to 1,220 Nm using a calibrated torque wrench and Loctite 270.
- Install the new hydraulic hoisting motor.
- Refill gearbox oil and reinstate the slip ring and hoisting limit switch.
- Fully re-tension the hoisting wire on the drum.
- Perform a dynamic load test at 36 tonnes and a static proof load test at 41 tonnes before returning the crane to service.
Execution & Delivery
The project was executed entirely at anchorage under full Alatas field supervision. When the standard mechanical press was unable to release the seized gearbox, the team employed a hydraulic press and jack before fabricating custom expanders on site to safely free the drum-and-gearbox assembly.
Following installation, comprehensive functional checks and proof load testing verified the rebuilt hoisting system before the crane was returned to operational service.
Outcome
The hoisting gearbox and hydraulic motor replacement was completed successfully, restoring the crane’s lifting capability and operational reliability. The crane successfully passed both dynamic and static proof load tests, confirming safe operation and allowing it to return to full cargo-handling duty without requiring deviation to a shipyard.
Benefits Delivered
- Returned the crane to full operational duty without requiring deviation to a shipyard.
- Restored reliable hoisting performance and operational capability.
- Successfully removed a seized gearbox using engineered removal techniques and purpose-fabricated expanders.
- Completed dynamic and static proof load testing to verify safe crane operation.
- Minimized operational disruption by completing the repair at anchorage.
- Delivered a complete turnkey field service solution from engineering through commissioning.