| Category | Details |
|---|---|
| ALATAS’ SERVICE | Managed Crane Contracts |
| LOCATION | EMEA / United Kingdom / North Sea |
| EQUIPMENT | Offshore Pedestal Box Boom Crane |
| BRAND / MODEL | Liebherr / RL 20(10)-20(30) EX |
Overview
Alatas UK mobilized technicians offshore to complete a prime mover changeout on a Liebherr offshore pedestal crane in the North Sea. The project included engineering preparation, rigging and scaffolding coordination, replacement of the prime mover, crane commissioning, and a full 5-tonne SWL load test before returning the crane to service.
Background
Crane operators reported that the crane was not performing as expected when the slewing, luffing, and hoisting functions were operated simultaneously. The crane was described as becoming “sluggish,” with a noticeable loss of speed across the functions.
An initial investigation identified that the crane’s prime mover was operating at temperatures above expectations. The client subsequently opted to replace the prime mover in an effort to improve crane performance.
Alatas’ Solution
The Alatas UK Project Engineering team developed the procedures and engineering work pack for the prime mover changeout, including the required risk assessments.
Lift plans were provided by the client, with Alatas supplying the associated rigging equipment in accordance with the approved lifting arrangements. Alatas Engineering also identified the scaffolding requirements and coordinated the scaffold design, erection, and dismantling at the appropriate stages of the project, supported by the Alatas Senior Service Technician and offshore scaffolding team.
The replacement prime mover was supplied by the client, while Alatas provided the remaining materials and equipment required to complete the work, including the load-testing equipment.
Alatas technicians were mobilized offshore to complete the changeout. Following installation, functional checks were carried out before the crane underwent a full 5-tonne SWL load test from minimum through maximum radius.
Job Scope
- Develop the engineering work pack and risk assessments for the prime mover replacement.
- Mobilize the Alatas service team offshore.
- Coordinate scaffold design and erection.
- Set up rigging in accordance with the client-provided lift plan.
- Remove and replace the crane prime mover.
- Remove rigging following completion of the changeout.
- Coordinate scaffold dismantling.
- Perform crane functional checks.
- Conduct a full 5-tonne SWL load test from minimum through maximum radius.
- Return the crane to service.
Execution & Delivery
The project was delivered through coordination between the Alatas UK Project Engineering team, UK Service team, Flying Squad Technicians, and WELS team.
Engineering preparation, offshore access, rigging, equipment supply, installation, commissioning, and load testing were coordinated to support the safe completion of the prime mover changeout. Following installation, the crane completed functional checks and the required full SWL load test before being returned to service.
Outcome
The prime mover changeout was completed offshore, followed by crane commissioning and functional verification. The crane completed a 5-tonne SWL load test across its operating radius, allowing it to be returned to service following completion of the work.
Benefits Delivered
- Completed the prime mover changeout offshore.
- Coordinated engineering, rigging, scaffolding, and field service activities.
- Provided the supporting materials, rigging, and load-testing equipment required for the project.
- Verified crane operation through post-installation functional checks.
- Completed a full 5-tonne SWL load test from minimum through maximum radius.
- Returned the crane to operational service following successful testing.