| ALATAS’ SERVICE | Field Service / ENGINEERING |
| LOCATION | EMEA / SPAIN / LAS PALMAS, GRAN CANARIA |
| EQUIPMENT | OFFSHORE CRANES SHIPYARDS |
| BRAND / MODEL | 100 TE PEDESTAL KNUCKLE BOOM / NOV OC4000KCE |
INTRODUCTION
Alatas was requested by a valued customer to remove a damaged slew bearing and install a new replacement slew bearing.
BACKGROUND
During routine inspection, the client discovered damaged teeth on the slew bearing. As an immediate measure, one slew motor was replaced, and the crane was downrated by the OEM until permanent repairs could be carried out.
ALATAS’ SOLUTION
Alatas engineered and deployed a customized jacking system with two lifting points and designed a dedicated removal table. The table was welded to the pedestal to provide a stable platform, and the crane chassis was carefully jacked up to allow for safe removal and installation.
The damaged slew bearing was removed using Alatas lift plans, and a new bearing was installed with the fixed soft spot aligned in the correct position. Following installation, slew bolts were torqued, backlash settings were adjusted, and the crane underwent functional and deflection testing before being prepared for PLT (Proof Load Test).
JOB SCOPE
- Fabrication of lifting eye pads for lifting side plate, gearbox, and motor
- Installation of jacking system on port and starboard pedestal locations
- Temporary modification of main boom cylinder hydraulics for jacking clearance
- Welding of removal table onto crane pedestal
- Jacking crane chassis up by 125 mm to create bearing clearance
- Removal of damaged slew bearing and lowering to quayside
- Installation of new slew bearing with correct soft spot alignment
- Lowering crane chassis and reinstallation of slew bolts
- Reinstatement of hydraulics
- Setting of slew motor backlash
- Completion of full functional test
- Execution of slew deflection test
- Preparation of crane for Proof Load Test (PLT)
Knuckle Boom Pedestal Crane Slew Bearing Changeout gallery