ALATAS’ SERVICEFIELD SERVICE
LOCATION  EMEA / UK / ABERDEEN SOUTH HARBOUR
EQUIPMENT  MERCHANT SHIPPING – SHIP CRANES / OFFSHORE CRANES
BRAND / MODEL  KNUCKLE BOOM CRANE / NOV OC3432KSCE

INTRO

The customer reported false Safe Load Indicator (SLI) readings from the main hook block load-monitoring system.


BACKGROUND

The main hook block SLI system was producing inaccurate readings. Upon inspection, the top load-sheave was identified as faulty. An attempt was made to remove the defective load pin; however, the pin was seized and could not be extracted through standard methods.


SOLUTION

As there was no hot work restrictions on this vessel, ALATAS recommended the use thermal lancing to remove the seized pin. The process involved burning a hole through the center of the pin to allow the use of a threaded bar and pulling pot to extract the pin safely and with controlled force.


JOB SCOPE

Work was conducted by the Aberdeen Project Engineering team, ALATAS Ports team, and ALATAS Bradford Equipment team.
Scope of work included:

  • New sheave bush installation
  • Removal of load-pin ancillaries
  • Rope tie-back from the sheave
  • Placement of fire blankets to protect surrounding areas
  • Load-pin lancing (hot-work removal)
  • Load-pin extraction using threaded bar and pulling pot
  • Cleaning of boom-sheave pin clevises
  • Ovality check on boom-sheave pin clevises
  • Installation of new sheave
  • Installation of new load pin
  • Functional test
  • Load test and SLI calibration