BACKGROUND
The vessel is equipped with Liebherr CBW Deck Cranes, each with a Safe Working Load (SWL) of 40 tons in hook mode and 32 tons in grab mode. These cranes are used primarily for heavy-duty grab operations. The hoisting winch gearbox failed on one crane, and the winch drum showed significant wear. Consequently, the owner decided to replace the entire hoisting winch assembly, including the winch frame, rather than just the planetary gearbox, to streamline installation and reduce repair time.
The hoisting winch is located at the top of the crane’s slewing column. The repairs are to be conducted at Singapore Anchorage, requiring the use of a floating crane.
ALATAS’ SOLUTION
ALATAS has extensive experience performing major crane repairs at anchorage, particularly those involving floating crane support. At the owner’s request, Alatas Singapore mobilized their Senior Liebherr Crane Service Engineer, a repair team, and necessary equipment to complete the repairs at Singapore Anchorage.
JOB SCOPE
- Scaffolding Setup: Erected scaffolding around the crane column.
- Hydraulic Motor Preparation: Disconnected hoses from the hydraulic hoisting motor.
- Limit Switch Box Removal: Removed the limit switch box from the hoisting winch.
- Frame Support Welding: Welded strong backs to aid in jacking out the winch frame mounting pins.
- Winch Assembly Removal: Arranged for a floating crane to lift the entire winch assembly down to the deck.
- Hydraulic Motor Transfer: Installed the existing hydraulic motor, complete with valve block, onto the new hoisting winch.
- New Winch Installation: Used the floating crane to position the new winch assembly on the mounting base at the top of the crane tower.
- Alignment and Frame Pin Re-installation: Welded an “A” frame to align the hoisting winch using chain blocks, then re-installed the winch frame pins.
- Final Assembly: Removed the “A” frame and reconnected all hydraulic hoses and fittings.
- Fluid Fill: Filled the hoisting gearbox with gear oil and the motor casing with hydraulic oil.
- Crane Testing: Started the crane and tested the hoisting winch in the presence of the vessel superintendent.
- Completion: Confirmed that the new winch is operating well, and the job was completed to the satisfaction of the superintendent engineer.