Overview
Alatas was engaged to replace the crane travel wheels on a Liebherr Ship-to-Shore (STS) container crane as part of a planned asset reliability program. With the existing wheel assemblies approaching the end of their operational life, the project required a carefully engineered methodology to safely lift and support the crane, enabling the wheel assemblies to be removed and replaced without compromising the crane’s structural integrity.
Background
The existing crane travel wheel assemblies had reached the end of their service life and required replacement to maintain reliable crane travel and reduce future wear on the wheel-and-rail system.
Due to the size and weight of the STS crane, replacing the wheel assemblies required a bespoke lifting methodology capable of safely supporting the crane throughout the operation. Extensive engineering planning was therefore required before any site work could commence.
Alatas’ Solution
A key element of the project’s success was the involvement of the Alatas Engineering Design team from the earliest planning stages. Before mobilization, detailed engineering assessments were completed to develop a bespoke lifting methodology capable of safely supporting the crane while the wheel assemblies were removed and replaced.
The engineering team produced comprehensive calculations, structural assessments, lifting arrangements, fabrication drawings, and installation documentation to verify that all temporary works and lifting equipment were suitable for the imposed loads. This engineering-led approach minimized project risk and ensured every stage of the wheel replacement could be completed safely and efficiently.
Following completion of the engineering design, Alatas delivered the project under full turnkey management, providing engineering, lifting operations, installation, alignment, and commissioning.
Job Scope
- Develop engineering calculations and structural assessments.
- Produce lifting arrangements, fabrication drawings, and installation documentation.
- Mobilize specialist lifting equipment and engineered support frames.
- Lift and support the crane using the engineered temporary works.
- Remove the existing crane travel wheel assemblies.
- Inspect axles, bearings, and mounting arrangements.
- Install and align replacement wheel assemblies.
- Verify wheel geometry and rail engagement.
- Perform functional testing before returning the crane to service.
All work was completed in accordance with project-specific RAMS, lifting plans, and engineering documentation.
Execution & Delivery
The project was executed under full Alatas project management using the engineered lifting methodology developed during the planning phase. Close coordination between the Engineering Design team, project management, and field service personnel ensured the crane remained safely supported throughout the wheel replacement process.
The engineered temporary works and lifting arrangements enabled the wheel assemblies to be replaced efficiently while maintaining the structural stability of the crane and minimizing operational downtime.
Outcome
The wheel replacement program was completed safely and successfully, restoring smooth crane travel and improving the long-term reliability of the crane travel system. The engineered lifting methodology enabled the work to be completed efficiently while maintaining the structural integrity and stability of the crane throughout the operation.
Benefits Delivered
- Bespoke lifting methodology developed by the Alatas Engineering Design team.
- Safe temporary works designed specifically for the project.
- Restored smooth and reliable crane travel.
- Reduced wheel and rail wear.
- Improved machine uptime and operational availability.
- Extended the service life of the crane travel system.
- Delivered a complete turnkey solution from engineering design through commissioning.