ALATAS’ SERVICEFIELD SERVICE
LOCATION  ASIA / HONG KONG SAR / CHINA / ANCHORAGE
EQUIPMENT  LIFEBOAT AND DAVIT
BRAND / MODEL(5.70*2.30*1.10M) 25 Person

Introduction

Alatas Hong Kong was requested to perform a load test on the vessel’s lifeboat and davit system.

Background

The load test was part of the vessel’s 5-year periodic lifeboat inspection.

Alatas’ Solution

Alatas Hong Kong’s engineering team completed the lifeboat and davit load test, ensuring compliance with the requirements.

Job Scope

  1. Preliminary Checks: Before starting the load test, the water bag overflow valve and weight capacity were tested using Alatas’ calibrated load cell, as requested by the Class surveyor. The water bag’s weight capacity was confirmed at 375 kg.
  2. Lifeboat Setup: The vessel’s crew secured the lifeboat on the starboard (STBD) side using belts.
  3. Water Bag Placement: Seven empty water bags were placed inside the lifeboat and connected to the water supply via a manifold.
  4. Filling Water Bags: The water bags were filled to a total of 2.5 tonnes (equivalent to 6.6 water bags at 375 kg each).
  5. Davit Winch Testing: The vessel’s crew performed static and dynamic brake tests on the davit winch at 2.5 tonnes. Results were satisfactory.
  6. Lowering to Sea Level: The lifeboat was lowered to the sea level.
  7. Boarding the Lifeboat: Alatas’ engineer and vessel crew boarded the lifeboat using a pilot ladder.
  8. Release into the Sea: The lifeboat was unlatched and released into the sea for further testing.
  9. System Check: The vessel’s crew tested the lifeboat’s engine, sprinkler system, and other functions according to their procedures.
  10. Securing the Lifeboat: After testing, the crew latched and reset the lifeboat.
  11. Draining Water: The water was drained from the water bags using a pneumatic pump.
  12. Lifeboat Retrieval: The lifeboat was lifted and secured back on board.
  13. Removal of Equipment: The water bags and other testing accessories were removed from the lifeboat.
  14. Port Side Testing: The same procedure was repeated on the port side lifeboat.
  15. Approval: The class surveyor approved the tests for both the starboard and port side.
  16. Equipment Return: The water bags and testing equipment were packed, and the Chief Officer was informed to transfer them back to Alatas’ workshop.
  17. Completion: The report was signed, and the team disembarked from the vessel.