Maintenance of Starboard Side Bunker Crane in Turkey Yalova

ALATAS’ SERVICEFIELD SERVICE
LOCATION  EMEA / TURKEY / YALOVA
EQUIPMENT  SHIP CRANES / BUNKER CRANE

Introduction

Alatas Turkey recently completed a major maintenance project on Bunker Cranes, focusing on critical inspections and overhauls of hoisting mechanisms. The engineering team meticulously cleaned and reassembled essential components, renewed slewing bolts, and addressed key issues such as a non-operational hoisting down limit and malfunctioning K5 Time Delay Relays. By replacing these relays and a capacitor, the team ensured the crane’s optimal performance. This comprehensive maintenance underscores Alatas Turkey’s dedication to quality service and guarantees the crane’s reliable operation for the customer.

Background

The customer contacted Alatas Turkey for maintenance on their Bunker Cranes. The scope included checking spare parts, replacing components, and overhauling hoisting movements and sheaves.

Alatas’ Solution

Upon arrival at the vessel and completing shipyard entry procedures, Alatas Turkey’s engineering team held a meeting to plan the work. The team then proceeded with dismantling, assembling, inspecting, and cleaning the necessary parts, and replaced components as needed.

Job Scope

  1. Initial Assessment:
    • After the meeting, the team inspected spare parts and began dismantling necessary components.
    • An overhaul and deficiency check were conducted for inoperative sheaves.
  2. Hook Block and Sheaves:
    • The hook block was dismantled.
    • The hook sheave was reassembled after adjustments to new equipment, ensuring sheave friction was eliminated to prevent future issues.
    • Three sheaves were cleaned, inspected, and reinstalled.
  3. Slewing Bolts:
    • Renewed both upper and lower slewing bolts.
  4. Limit and Relay Issues:
    • Limit tests revealed that while the hoisting upper limit was functioning, the hoisting down limit was not operational.
    • The K5 Time Delay Relays showed signs of smoking during hoisting movements. To resolve this, both K3 and K5 Time Delay Relays were replaced with new ones, and a faulty capacitor was also replaced.
  5. Final Steps:
    • After completing all repairs and replacements, the crane was thoroughly tested.
    • The crane was then delivered back to the customer by Alatas Turkey.