| ALATAS’ SERVICE | FIELD SERVICE |
| LOCATION | EMEA / TURKEY / YALOVA |
| EQUIPMENT | SHIP CRANES / GANTRY TROLLEY / MONORAIL CRANE / BUNKER CRANES |
| BRAND / MODEL | EGC115-4-9.5 / PC12-50/25-2,5/4,8 / MOB-B1500 ACC/PC5 |
INTRODUCTION
ALATAS Turkey engineers arrived at the vessel and, following standard security procedures, commenced the scheduled maintenance operations. The scope included the renewal of components, replacement of incorrectly installed clamps, and dismantling of various parts. All dismantled components were transferred to the dry dock area in preparation for delivery to the ALATAS Turkey workshop.
BACKGROUND
The customer contacted ALATAS Turkey for the maintenance of the Monorail and Bunker Cranes (Starboard and Portside), as well as for the renewal and replacement of specific parts.
ALATAS’ SOLUTION
Upon arrival, ALATAS Turkey’s engineers conducted a thorough inspection and proceeded with dismantling and maintenance operations based on their findings.
JOB SCOPE
1. Starboard Crane
- Slewing bearing bolt maintenance was carried out.
- An incorrect dust seal clamp was identified and replaced with one of the correct size, supplied by ALATAS.
2. Portside (Ptsd) Boat Winch
- The replacement hoses delivered to the vessel had incorrect connection fittings.
- Clamp sizes were adjusted and corrected by ALATAS.
- Slewing bearing bolts were renewed.
- All hydraulic hoses were removed and retained as samples.
- Dismantling included the hoisting gearbox, slewing main pump, and electric motors.
- During the pump dismantling, significant contamination was found inside the oil tank.
3. Monorail Crane
- Work began with the removal of hoisting wires.
- Components dismantled included:
- Gearboxes
- Hoisting electric motor
- Hoisting drums
- Trolley gear electric motor
- Starboard side hook block
- Trolley gearbox
- Pinion gears (both sides)
- All dismantled parts were transferred to the dry dock and prepared for transport to the ALATAS workshop.
- Components arrived at the workshop at 16:00 via agency delivery.
- Bearings, seals, and other parts were taken as samples; new replacements were ordered.
- Hook block sheave bearings were removed for sampling.
- During dismantling of the portside hoisting gearbox electric motor, water ingress was discovered and maintenance was performed.
- In addition to mechanical repairs, selected parts underwent cleaning, repainting, and structural reinforcement at the workshop.
- Mounting of the overhauled parts was completed onboard.
- Load and functional testing of the Monorail Crane was successfully carried out.
4. Bunker Crane (Port Side)
- The hoisting gearbox was dismantled and sent to the workshop for maintenance.
- After servicing, the gearbox was reinstalled onboard.
- Hydraulic hose connections were re-established.
- The slewing clamp was replaced with a new one.
Monorail Crane and Bunker (Stbd/Ptsd) Crane Maintenance—Türkiye gallery


Renewal, incorrect clamp size