NMF Deck Crane Jib-Foot Bearing Changeout

CategoryDetails
ALATAS’ SERVICEField Service
LOCATIONWWA, Singapore
EQUIPMENTDeck Crane – Jib-Foot Bearing Assembly
BRAND / MODELNMF/DK II 150016/70033
VESSELBBC TEXAS
CRANECrane No. 2

Overview

Alatas Singapore completed the replacement of the jib-foot bearing assemblies on both sides of Crane No. 2 aboard the BBC TEXAS at WWA, Singapore. The work involved securing the boom and boom hinge assembly, removing the existing hinge pins and bearing assemblies, installing new bearing housings and pins, and completing functional testing before returning the crane to service.

Background

Alatas Singapore was engaged to replace the jib-foot bearings on both sides of Crane No. 2. Before work commenced, the Alatas service engineer met with the vessel’s captain and chief engineer to review the job scope and complete the required toolbox talk and risk assessment. A hot-work assessment was also completed, and the necessary documentation was issued before hot work began.

The crane was positioned on its boom rest, the hoisting and luffing wire ropes were slackened, and scaffolding was erected beneath both boom hinge bearing areas to provide safe access. The spare parts available onboard were also checked and confirmed before the changeout proceeded.

During removal, the hinge pins could not initially be extracted using hydraulic jacking, requiring Alatas to adapt the removal method to complete the changeout.

Alatas’ Solution

Alatas prepared both hinge pin areas using hot-work tools and heat treatment to remove rust particles and paint. A jacking nut was welded to the center of the left-side pin, and pad eyes were welded to the crane structure to secure the boom and boom hinge assembly with rigging equipment.

The left-side pin was initially jacked using a 100-tonne hydraulic jack with a portable HPU. At 500 bar, the M42 nut came away from the pin without moving it from its original position. A further attempt using an M36 stud at 600 bar resulted in the stud breaking, again without releasing the pin. Alatas therefore proceeded to gouge out the left-side pin.

The same hydraulic extraction method was attempted on the right-side pin. At 600 bar, the M36 stud broke and the pin remained in position. The right-side pin was therefore also removed by gouging.

Following pin removal, the existing bearing assemblies were lowered to the hatch cover using chain blocks. Cleaning work was completed before the new bearing housing assemblies were lifted into position and installed at the jib foot. New hinge pins were aligned and installed, secured with locking plates, and the new boom hinge mounting bolts were tightened to 3,300 Nm using hydraulic torque tools.

Job Scope

  • Conduct onboard coordination, toolbox talk, risk assessment, and hot-work preparation.
  • Position Crane No. 2 on the boom rest and slacken the hoisting and luffing wire ropes.
  • Erect scaffolding beneath both boom hinge bearing areas.
  • Verify the spare parts available onboard.
  • Prepare the hinge pin areas using hot-work tools and heat treatment.
  • Secure the boom and boom hinge assembly using welded pad eyes and rigging equipment.
  • Attempt hinge pin extraction using a 100-tonne hydraulic jack and portable HPU.
  • Gouge out the hinge pins after hydraulic extraction proved unsuccessful.
  • Remove the existing bearing assemblies using chain blocks.
  • Carry out cleaning work before installation.
  • Install the new jib-foot bearing housing assemblies.
  • Align and install the replacement boom hinge pins and locking plates.
  • Install new boom hinge mounting bolts and torque to 3,300 Nm using hydraulic torque tools.
  • Apply grease to both pins and confirm that the boom hinges are well-greased.
  • Remove the rigging equipment, temporary pad eyes, and scaffolding.
  • Function test Crane No. 2 with an empty hook.

Execution & Delivery

Alatas Singapore carried out the service attendance from September 16 to 21, 2026, at WWA, Singapore. The work included scaffolding, rigging, hot work, hydraulic jacking, pin gouging, chain-block handling, installation, alignment, hydraulic torqueing, lubrication, and final functional testing.

A key challenge was the removal of the hinge pins. When hydraulic jacking at pressures of up to 600 bar failed to release them, Alatas changed the removal method and gouged out the pins. This allowed the existing bearing assemblies to be removed and the replacement assemblies and pins to be installed.

Following installation, grease was applied to both pins, and the boom hinges were confirmed to be well-greased. The rigging equipment, temporary pad eyes, and scaffolding were then removed in preparation for functional testing.

Outcome

The jib-foot bearing changeout on Crane No. 2 was completed successfully. The crane was tested with an empty hook in the presence of the captain and chief officer.

No abnormal sound was observed from the boom hinge bearings during testing, and the service report recorded the test as satisfactory and the crane as working well following completion of the work.

Benefits Delivered

  • Completed replacement of the jib-foot bearing assemblies on both sides of Crane No. 2.
  • Adapted the removal method when hydraulic jacking was unable to extract the hinge pins.
  • Installed new bearing housing assemblies and replacement hinge pins.
  • Installed new boom hinge mounting bolts and tightened them to 3,300 Nm using hydraulic torque tools.
  • Applied grease to both pins and confirmed the boom hinges were well-greased.
  • Verified crane operation through empty-hook functional testing.
  • Confirmed no abnormal sound from the boom hinge bearings during the final test.
  • Returned Crane No. 2 to satisfactory operation following completion of the changeout.