Liebherr BOS Offshore Crane CMS Upgrade & Obsolescence Management

Overview

Alatas was engaged to deliver a full Crane Management System (CMS) upgrade on a Liebherr BOS offshore crane, originally manufactured in the 1980s. The crane was operating with its original TTL-based control system, which had become increasingly obsolete, with unsupported hardware, limited spare part availability, reduced reliability, and restricted diagnostic capability.

The project focused on removing the ageing TTL control architecture and replacing it with a modern, fully supported CMS platform designed to improve operational reliability, enhance diagnostics, and future-proof the crane for continued offshore service.



Project Objectives

The key objectives of the project were to:

  1. Remove the obsolete original TTL control system
  2. Upgrade the crane to a modern, fully supported CMS platform
  3. Improve operator interface and overall usability
  4. Enhance diagnostics and fault-finding capability
  5. Introduce load and system data recording for operational visibility
  6. Enable remote login support for diagnostics and troubleshooting
  7. Minimise downtime during installation and commissioning
  8. Deliver measurable cost savings and improved machine uptime

Scope of Work

Alatas delivered a structured CMS upgrade programme including:

  • Detailed site survey and obsolescence assessment
  • Removal of the original TTL-based control hardware and legacy CMS components
  • Design and configuration of a new CMS architecture
  • Installation of upgraded control hardware and HMI systems
  • Integration with crane control and safety systems
  • Development of improved operator displays and control logic
  • Implementation of load monitoring and system data recording functionality
  • Integration of remote access capability for offsite support and diagnostics
  • Full system testing, commissioning, and validation
  • Provision of operating manuals and engineer access documentation

The upgraded system provided significantly improved control visibility, system reliability, and long-term maintainability.


Execution & Delivery

The project was delivered under full Alatas project management, with careful planning to minimise operational disruption. The works were executed using a phased approach, allowing the crane to be temporarily returned to service mid-project to support essential lifting operations before final completion.

All equipment, tooling, and materials were planned, procured, and mobilised offshore in advance to support efficient execution within the constraints of the offshore environment.

All works were completed under approved RAMS and in accordance with offshore working practices.


Outcome

The upgraded CMS was successfully commissioned, eliminating the risks associated with the obsolete TTL control system and replacing it with a modern, fully supported platform.

The introduction of enhanced diagnostics, load and system data recording, and remote login capability improved both operational visibility and long-term maintenance support while ensuring continued crane availability throughout the project.


Benefits Delivered

  • Elimination of risks associated with obsolete TTL control hardware
  • Improved machine uptime through enhanced reliability and diagnostics
  • Reduced reactive maintenance and fault-finding time
  • Real-time load and system data recording for operational insight
  • Remote login support enabling rapid troubleshooting without offshore mobilisation
  • Minimal disruption through phased execution allowing continued crane operation
  • Future-proofed crane management system with long-term supportability
  • Fully managed turnkey CMS upgrade delivery