Urgent Boom Rope Changeout on Liebherr BOS Crane Offshore in Senegal

ALATAS’ SERVICEFIELD SERVICE / ENGINEERING
LOCATION  EMEA / SENEGAL / MAURITANIA / WEST AFRICA – OFFSHORE
EQUIPMENT  Offshore / Crane / Luffing Winch / Aux Winch
BRAND / MODELOFFSHORE PEDESTAL CRANE LIEBHERR BOS 2600-30 LIT

INTRODUCTION

Alatas was employed to repair an international oil company’s lone crane on their jack-up platform in response to a breakdown. We surveyed the site, engineered a procedure, and mobilized personnel and equipment internationally to replace the crane rope successfully, test it, and return the crane to service.

BACKGROUND

Alatas’ resident crane technicians on the client’s asset identified wear on the rope and some broken wires as part of their planned maintenance routines. As a result, the crane was removed from service for safety reasons.

ALATAS’ SOLUTION

Alatas mobilized a senior service technician to inspect and verify the condition of the rope. Additionally, since the rope had never been changed before and there were no other cranes on the platform to support the replacement, a novel procedure and lift plan had to be developed to ensure a safe change-out.

Alatas specified and supplied all necessary equipment and consumables for the boom rope replacement. We also urgently mobilized crane service technicians to complete the job quickly and safely, minimizing disruption to client operations.

JOB SCOPE

  • The client notified Alatas Global Resources and Alatas UK of the breakdown and the support requirement.
  • Alatas UK mobilized a senior service technician to verify the rope’s condition, identify procedural steps for the replacement, and assist with creating permits and risk assessments.
  • Alatas UK provided an engineering work pack, sourced materials and equipment, and transported them to the site via road and air.
  • Alatas UK supported the client’s Root Cause Analysis (RCA) investigation.
  • Alatas UK, Alatas Indonesia, and Alatas US were contacted to supply crane technicians.
  • Alatas US provided the fastest personnel mobilization and deployed them to the site.
  • The crane was removed from service.
  • Permits were issued, and a toolbox talk was conducted.
  • Limits were disconnected, the rope was replaced, and limits were reinstated.
  • The crane underwent function testing.
  • A service report was issued.
  • Personnel were demobilized, and equipment was backloaded.